Delivering the Master Plan2026-04-22T15:12:43+10:00

DELIVERING THE MASTER PLAN

Project updates

Quarry Loop underway

Construction has commenced on the Quarry Loop – a shared path encircling the rim of the quarry. This picturesque route, with some steep inclines, is designed for walking, running, cycling and dog walking, offering scenic views of the quarry lake, the surrounding forests and the volcanic diatreme.

The Quarry Loop is proudly funded by the NSW Government in association with Hornsby Shire Council.

Old Mans Valley

Work on the Old Mans Valley Field of Play is underway. Co-funded through a Thriving Suburbs Grant from the Australian Government, this project will deliver a recreational playing field, bike pump track, new picnic facilities and amenities.

20262026-04-22T15:19:39+10:00

Hornsby Park continues to take shape

Exciting changes are taking shape at Hornsby Park as we prepare to open the first precinct of this brand new space for the community.


Finishing touches at the Crusher Plant Precinct

We’re putting the final touches on the area surrounding the historic Crusher Plant building, featuring the spectacular Southern Lookout. This space will soon provide visitors with breathtaking views across the former quarry.

Current works include improvements along Quarry Road to establish a welcoming arrival plaza for visitors.

20252026-03-23T14:24:26+11:00

July 2025

The Southern Lookout takes shape

We are excited to share a behind-the-scenes look at the construction and transportation of the Southern Lookout viewing deck and access stairs, located at the historic Crusher Plant site at Hornsby Park.

Our contractors are installing these landmark features, which will transform the way residents and visitors experience the bushland setting on the site of the old Hornsby Quarry.

These prefabricated steel structures have been expertly designed for durability, safety, and accessibility, and represent a major milestone in the delivery of Hornsby Park.

The Southern Lookout will offer panoramic views across the former Hornsby Quarry and surrounding bushland, creating a unique space that connects people with the natural landscape and honours the area’s heritage.


June 2025

We prepared a Review of Environmental Factors (REF) to complete Embellishments – Stage 2 at Hornsby Park. These Stage 2 works will build upon the above works across the park and are a vital next step in the path to realising the Master Plan. The proposed works in Old Mans Valley (OMV) will start to fill in some of the remaining pieces of the park.

The Hornsby Park Embellishment – Stage 2 REF assesses possible impacts the project will have on the environment and details steps to be carried out to avoid, minimise, or mitigate those impacts.

Comments closed on Friday, 4 July 2025.

There were 61 submissions received in response to the exhibition. 50 of the submissions focus on the mountain biking aspects of the proposal with the remaining 11 covering broader topics.  All except one expressed some level of support for the proposal. The one submission that expressed opposition to the REF highlighted matters covered by the ten other non Mountain Bike submissions that provided a mixture of views; including concerns, suggestions and recommendations on various topics. Note: two submissions received from the same person on the same day have been combined as one submission.


May 2025

Exciting progress at Hornsby Park

Hornsby Park continues to take shape, with major milestones bringing us closer to a vibrant new recreational space for the community.

The Crusher Plant area draws closer to completion and now features picnic tables and barbecues, which will provide a welcoming spot for visitors to relax. Ongoing investment in vegetation management and habitat creation is enhancing the natural landscape, while the construction of the Western Lookout and Boardwalk is almost complete, with tracks and trails leading to Rosemead Road.

Construction of the Southern Lookout viewing platform is well underway. This striking structure, with its 14-metre-high tapered steel columns, 13-metre flight of stairs and 42-metre-long viewing deck, will offer breathtaking panoramic views across the quarry and surrounding bushland. Meanwhile, work is progressing on the North-Western Lookout, adding even more scenic vantage points to the park.

The final stage of the Hornsby Heritage Steps restoration is advancing, ensuring the long-term durability of these historic steps.

In more great news, work will soon begin on a circulation path around the old quarry, designed for walking and cycling. This addition will enhance the enjoyment of Hornsby Park for residents and visitors alike.


30 April 2025

Update regarding Southern Lookout Deliveries on Quarry Road, Hornsby

The deliveries relating to the Southern Lookout, originally scheduled to start on Thursday 1 May, have been delayed due to wet weather.

The nighttime truck deliveries have therefore been adjusted as follows:

  • two trucks scheduled to arrive in Hornsby between 11pm and 1am on Friday 2 / Saturday 3 May
  • one truck scheduled to arrive in Hornsby between 11pm and 1am on Monday 5 / Tuesday 6 May

Two further deliveries will be completed during the daytime on Tuesday 6 May / Wednesday 7 May.

The Quarry Road parking restrictions will be as previously advised.

Council apologises for any inconvenience that may be caused during the works.


8 January 2025

Shortly after we started the track works in August 2024, we discovered a nesting pair of Powerful Owls.

As noted in November 2024 – Construction work at Hornsby Quarry has been carefully planned and delivered to incorporate the needs of local Powerful Owls.

It has now been determined that, as is the case every year, the Powerful Owls and their chicks have left the Hornsby Quarry locale for their summer home.

We are therefore able to recommence the previously scheduled track works from Monday 13 January 2025.

The details are per our 19 August 2024 update.


January 2025

The Circulation Works REF was publicly exhibited from 2 December 2024 until 20 January 2025. The purpose of the exhibition was to provide the community with the opportunity to provide feedback on the REF which would then enable Council to consider any possible adjustments to the included elements. The Public Exhibition of the REF was advertised online via Your Say Hornsby, eNews, and the community were invited to provide feedback via an online submission form, in writing or via email.

There were 5 submissions received in response to the exhibition. One submission was very brief “Endorsed. A very well written REF, reads well easily.”. The other submissions provided a mixture of views; including concerns, suggestions and recommendations on various topics.

20242026-03-23T14:28:35+11:00

9 December 2024

Old Mans Valley, part of Hornsby Shire Council’s ambitious Hornsby Park project, will come alive as a vibrant Field of Play thanks to a Thriving Suburbs grant from the Australian Government.


December 2024

We have prepared a Review of Environmental Factors (REF) to complete Circulation Works at Hornsby Park. These Circulation Works will connect the rehabilitation and Stage 1 embellishment works through the completion of the Quarry Loop around the rim of the Quarry. This will enable visitors to safely experience the former quarry.

The Hornsby Park Embellishment – Circulation Works REF assesses possible impacts the project will have on the environment and details steps to be carried out to avoid, minimise, or mitigate those impacts.

Comments on the Hornsby Park Embellishment – Circulation Works REF closed on Monday, 20 January 2025.


November 2024

Powerful Owl

Construction work at Hornsby Quarry has been carefully planned and delivered to incorporate the needs of local Powerful Owls. The construction team, Council ecologists and Birdlife Australia are working diligently to ensure daily activities at the site are conducted with the utmost consideration for these magnificent birds. Ongoing monitoring of the owls is also undertaken to ensure a safe and suitable environment is maintained for the owls through the construction phase. Council is committed to preserving the habitat as part of the Vegetation Management Plan and Habitat Creation and Enhancement Plan that is being implemented on site. Combined, these plans, and the proactive measures being implemented will protect and support this important species.


19 August 2024

As part of the Stage 1 embellishment works for Hornsby Park, we will be upgrading an existing bush track to become a shared pedestrian / mountain bike connection from Rosemead Road (see 2 and 4a on the map).

An elevated boardwalk (4b) will complete the link to the Western Lookout. Another track (3) will provide a pedestrian link to the North-Western Lookout. Refer to the Stage 1 Embellishment REF for more detail.

The existing fire trail (1) will be used as the access path to deliver material to the works and there will be machinery moving up and down that fire trail from time to time. Our contractors will be working to keep the trail open for walkers and for emergency access. Care should be taken when walking through this area while the works are underway, which will take approximately one month overall (weather permitting).


3 July 2024

Work has commenced on the utilities at the western end of Quarry Road, as part of the development of the former quarry site.

When the works reach the junction of Quarry Road, Dural Street and Frederick Street within the next couple of weeks, a part of Dural Street will be need to be closed and traffic detours and management will be in place. Property access will be maintained at all times.


31 May 2024

We have prepared a Review of Environmental Factors (REF) under Part 5 of the EP&A Act, to undertake additional drainage works to the north-east of the Hornsby Quarry void to ensure that stormwater is safely conveyed through the site.

The REF was on public exhibition between 31 May and 30 June 2024. No submissions were received.

20232026-03-23T14:32:40+11:00

2 August 2023

As part of Local Government Week, we celebrated by showcasing a few of our team members from across Council.

Meet Project Manager, Trevor Carlyle-Hoggan


29 June 2023

Review of Environmental Factors (REF) Community Engagement Report

Following adoption of the Hornsby Park Master Plan in July 2021, Hornsby Shire Council resolved on 8 March 2023 to undertake Stage 1 Embellishment Works for Hornsby Park. It has been determined that the Stage 1 works can be approved under Part 5 of the New South Wales Environmental Planning and Assessment Act 1979 (EP&A Act).

This report summarises feedback and provides responses to submissions received by Hornsby Shire Council during the exhibition of the Hornsby Park Master Plan Stage 1 Review of Environmental Factors (REF).

The REF was publicly exhibited from 27 April until 25 May 2023. The purpose of the exhibition was to provide the community with the opportunity to provide feedback on the REF which would then enable Council to consider any possible adjustments to the Stage 1 elements. The Public Exhibition of the REF was advertised online via Your Say Hornsby, in the local print newspapers, eNews, and the community were invited to provide feedback via an online submission form, in writing or via email.

There were 17 submissions received in response to the exhibition. Seven of these expressed support for the proposal, two were opposed and eight submissions contained mixed views, suggestions or recommendations. Note: two submissions received from the same person on the same day have been combined as one submission.


9 March 2023

$27.9 Million First Stage for Hornsby Park Unveiled

At its general meeting on Wednesday 8 March, Hornsby Shire Council took significant steps forward in the delivery of its major project at Hornsby Park. Councillors determined to progress Hornsby Park by delivering an impressive canopy skywalk and cable bridge through the trees in 2024.

As per the Master Plan adopted in July 2021, Hornsby Park will become a major recreation destination which will be delivered in stages. Following extensive groundworks at the site, Council has responded to our community’s desire to be able to visit and enjoy the site as soon as possible by committing to deliver the first stage of the project.

The almost $28 million attractions will feature an impressive 400m canopy skywalk and cable bridge linking Hornsby Town Centre with the site of the old Crusher Plant on a fully accessible pathway immersing visitors into the bush. In this stage, Council will also begin developing the area around the Crusher Plant with a lookout, a lawn and play area, car park and toilet facilities. Plans also include additional bushwalking tracks and trails leading to two more lookouts to the west and north-west of the site. The first works are targeted to be open to the public in 2024.

“We are pleased that the first stage of this important project will be available next year for the community to enjoy. We have been working hard behind the scenes to make the site safe and preparing it for future uses. While the project as a whole will develop over time, we are excited that this new skywalk will give people to the opportunity to experience this unique destination of outstanding natural beauty and see this huge project taking shape,” said Hornsby Shire Mayor Philip Ruddock. “Delivering the project within a financially responsible framework is critical and we have worked with staff to ensure that we have safeguards in place to minimise any risk”.

20222026-03-23T14:35:39+11:00

December 2022

During 2022, earthworks, drainage and road works continued to progress in and around the quarry site but unfortunately, there were 304 days of delay added to the project timeline due to wet weather, Covid related and other global supply interruptions, site conditions and changes in scope.

As a result, construction of the park infrastructure that will deliver the Master Plan is unlikely to commence until 2025.

We understand the community are very keen to start enjoying the site. Therefore, given the construction delays and taking into account feedback we received about Hornsby Park during the Special Rate Variation engagement, Councillors are exploring options for providing access to the site as early as possible.

In parallel, commercial opportunities are being identified to help fund some elements of the project, during both the build and operating stages.

Southern lookout

Video courtesy of Dunsteel Group.

Timelapse videos

Civil Works Updates

2019

November 2019

Hornsby Quarry Rehabilitation Works Development Application – Response to Submissions and Revised Project Scope (RTS) was open for public review and comment from Friday 22 November 2019 until 13 January 2020. The RTS and additional submissions were then assessed by an independent planner and reported to the Sydney North Regional Planning Panel.

What the revisions mean November

  • Reduced extent of earthworks which preserves more trees across the site
  • A lower solution for landform within the quarry, which preserves more of the dramatic cliff faces on all sides, including the eastern diatreme feature.
  • A shorter construction timeframe, down from 24 months to 21 months, and reduced impacts associated with construction.

Importantly, we are still on track to deliver the first stage of the parkland creation in 2023, turning the local landmark into a spectacular new open space for the community to enjoy.

View the Hornsby Quarry development application


April 2019 – Hornsby Quarry Development Application and EIS

NorthConnex finished delivery of fill material to Hornsby Quarry in January 2019. Council with consultants prepared and lodged a Development Application (DA) with an  Environmental Impact Statement (EIS) for the next stage of works, to re-shape and stabilise the site, with the aim to deliver a safe landform that can be used for many different parkland activities.

The Development Application and supporting Environmental Impact Statement for the transformation of Hornsby Quarry were on Public Exhibition until 17 May 2019.

The DA had to be determined by the Sydney North Regional Planning Panel before Council could begin the earthworks.

The EIS also included some important recommendations about how to best protect the natural environment of the site, including the Ecologically Endangered Communities, preserve Aboriginal and non-Aboriginal heritage and manage potential impacts on nearby residents, businesses and the community.

2020

November 2020

The Hornsby Quarry Rehabilitation Works Development Application (DA/101/2019) was approved by the Sydney North Regional Planning panel.

2021

November 2021 – Notification of tree clearing

Bulk earthworks have commenced on the Hornsby Park site. The earthworks are necessary to re-shape and stabilise the site to make the park safe. As part of these works, the removal of some trees and vegetation is necessary.

These works will be carried out in line with the approved Vegetation Management Plan.

Work hours will be limited to those in the table below, to minimise noise and disruption to residents. Noise levels will be monitored throughout the project.

Temporary closure of mountain bike trails

Due to the earthworks, some mountain bike trails will need to be temporarily closed. Most of these trails should re-open within a week or two of their closure. The trails affected will be Lava Flow, Turkey Run and Jump Park.

Details on which sections will be closed, when and for how long will be updated regularly on our Hornsby Park MBT twitter feed https://twitter.com/HornsbyMBT.

November 2021 – Hornsby Park Drainage Upgrade Project

We prepared a Review of Environmental Factors (REF) to undertake drainage upgrade works around the north-eastern edge of the quarry void at Hornsby Park. A storm in 2020 caused significant scouring and erosion of the earth embankments and the collapse of a stormwater culvert (pipe) under the roadway. The drainage works are necessary to ensure that stormwater is safely conveyed through the site, safeguarding the site for future public use.

The drainage works have been designed for a 1 in 100 years rainfall event and include constructing culverts and open, rock lined channels. The drainage work will divert stormwater flow away from the quarry void, preventing future land slippage in large rainfall events and ensuring public safety is maintained. The area will be revegetated with local species.

The REF was exhibited between 27 October and 24 November, 2021 during which time four submissions were received.


September 2021

Council has appointed Ditchfield Contracting Pty Ltd to deliver bulk earthworks and stabilisation works for the Hornsby Park redevelopment. Works will commence on site this month.

These works will re-shape and stabilise the site and will deliver a safe landform that can be used for many different parkland activities.

Tasks include:

  • Bulk earthworks and associated civil works including construction of access tracks, drainage and retaining walls;
  • Quarry wall stabilisation works; and
  • Revegetation work

This stage is expected to be completed in mid-2023 (subject to weather).

View the Adopted Masterplan

2022

October/November 2022

October saw further rain events continue to impact progress across the site. Topsoiling works progressed with an additional drain required to redirect water seepage. In the quarry void, filling continued during dry periods and there was work to remove loose rock which will be used in the retaining wall material.

There was good progress across the site in November due to a very welcome spell of fine weather. Works included the placement of box culverts for the Old Mans Valley Drainage Diversion, topsoiling and earthworks on the Northern Spoil Mound.

The current date for Practical Completion is February 2024. This includes a delay of 304 days due to wet weather-related issues, supply chain issues and scope changes.


August/September 2022 – Unfavourable weather hampers progress

At the end of August the Bureau of Meteorology (BOM) confirmed that Sydney is on track for its wettest year ever after passing 2-metre milestone for only the fifth time.

The works underway at Hornsby Park are focussed on moving huge quantities of earth around to make the site safe and to create the platforms for future use.  When the soil becomes saturated, or underwater, work is impossible. This year we have already lost almost 120 working days as a result of wet weather. On 13 September the BOM officially declared that Australia’s east coast was experiencing the third La Niña weather system in a row, increasing the risk of rain and flooding  in the coming months (ABC News).

While every effort is being made to reduce the impacts of the weather through enhanced drainage solutions, until these are in place the site will continue to be inundated in major weather events.

We will continue to provide updates as to how this will impact timelines for the project while hoping that perhaps the BOM’s predictions won’t be so bad after all.

Pictures show how the Quarry Void has been flooded on two occasions this year, between which we’d just managed to get back to working on site, only to be delayed again.


February/March 2022 – Works delayed

During February and March 2022, Hornsby Shire local government area, including the Hornsby Quarry site experienced significant rainfall.

The rainfall over a one month period was 830mm which is over 70 percent of the annual average rainfall for Hornsby. The programmed works have been impacted as a result of this rainfall.

2023

October/November 2023

Works across the site have progressed well in October/November.

As part of the stabilisation stage of the project several retaining walls and barriers are being constructed. The purpose of these walls is to ensure safety for park users by providing edge protection from the sheer quarry faces and retaining the surrounding embankments and access roads.

Different construction methods have been employed for these walls.

Precast concrete panels have been used for speed of installation and safety of workers on the edge of the quarry faces, the largest of these panels being over 3m in height. Placing these panels on the edge of a cliff face requires precision and a very large crane.

Other concrete walls will be built onsite which involves constructing formwork, fixing steel reinforcement, and pouring concrete. During October/November works have commenced on a large retaining wall above the eastern quarry face.

Retaining walls across the Northern Mound have been completed using gabion baskets. These have been built by filling wire baskets with dark grey basalt quarry rock, in keeping with the natural rock at the quarry.


August/September 2023

Further progress has been made across the site following dry conditions in August/September.

September 2023 marks two years since the contractor began work onsite.

Key to having a functional site in the future is having safe access to all areas which will be designated as public space.

The road known as the Southern Access Track will be one of these important links around the site.

This road sits above the highest quarry face on the site and previously the size of vehicle using the track was quite limited.

Significant work was required to ensure that the road is protected from future erosion and can support the necessary pavement.

Long micropiles were installed deep into the ground to anchor and strengthen the road. The micropiles were then encased in concrete to form a beam on which the road pavement could be built and tied into.

As part of the works some of the road uphill slope was cut back to improve stability.

During August and September, this area was completed with the pouring of the concrete barrier and road pavement.

This will now allow safe access to this part of the site.


June/July 2023

Good progress has been made across the site following mostly dry conditions in June and July.

The project has been extended by 164 days due inclement weather since the project started in September 2021.

In order to ensure a safe environment for the future parkland it is critical to ensure that the former quarry walls are secured and stabilised. These stabilisation works have involved the installation of rock bolts and rockfall mesh across the walls and provision of minor rock fall catch fencing. These works together with regrading some excessively steep earth slopes will provide a safe space for future park embellishments.


April/May 2023

Good progress has been made across the site following mostly dry conditions in May. Progress in April was impacted by the public holidays for Easter and Anzac Day and inclement weather.

There has been sustained progress on the construction of the drainage network across the site. Works have included the installation of stormwater drainage pipes along the Northern Access Track and construction of major drainage structures such as inlet structures, track racks and headwalls.

Earthworks to reshape the land to its future form have continued in the Quarry Void and Old Mans Valley including some rock excavation works at the southern end of Old Mans Valley to create a future carpark.


February/March 2023

During February, the site was impacted by intense storms almost weekly. In one event, the site recorded over 30mm of rain within six minutes. These storms delayed the planned works and caused damage to existing works. With such severe rainfall events likely to continue impacting the site, it reinforces the need to provide significant drainage infrastructure within the site to deal with the large catchment of stormwater that enters the site from the adjoining areas.

During this period, there has been continued progress with the major trunk drainage works with Basin 1 & 2 now completed and the majority of the Reinforced Concrete Box Culverts now installed. Once completed, the trunk drainage system will transport stormwater through the site without causing damage to the adjacent environment and assets.

Other works have included continued earthworks on the main platforms in Old Mans Valley.


December 2022/January 2023

December saw good progress across the site due to a very welcome spell of fine weather. The site was closed over the Christmas / New Year period with work resuming on 9 January 2023.

However, the site was once again impacted by more heavy deluges. This again hampered works, slowing progress in January.

Works have included bulk earthworks across the site, further placement and backfilling of box culverts for the Old Mans Valley Drainage Diversion and topsoiling on the Northern Spoil Mound.

2024

August 2024 – October 2024

From August to October 2024 significant progress continued to be made across the site, with key elements being completed. All concrete road pavements on site were completed with the final section of the RL90 Road, western end completed in August.

All retaining walls including precast, cast in-situ and gabion basket walls have been finished with the final gabion baskets being placed along the Northern Access Track.

As the earthworks batters are finalised across the site, hydromulching is applied.

The hydromulching mixture contains wood fibre, mulch, fertiliser, seed, water, and a bright green non-toxic dye.

Hydromulching encourages quick seed germination across large open areas.  It does this by locking down the topsoil by forming a protective cover and allowing the seeds to take root, germinate and grow to full height.

This vegetation binds together the soil to prevent erosion especially on steep slopes.

Works on the installation of major trunk drainage structures including pits and pipes are progressing.


May 2024 – July 2024

Over the cooler months of May through July, solid progress has continued, despite regular periods of wet weather, including Sydney recording thirteen straight days with 3mm of rainfall or more at the start of May. This record was just short of the all-time record of sixteen days straight in 2022 and 1943. The project has been extended by 186 days due inclement weather since the project started in September 2021.

The proximity of Hornsby Park and the former quarry site to the Hornsby Town Centre adds to the value of this hidden gem.  The site is perfectly located barely half a kilometre away from Hornsby Station, a major public transport node.  Start to appreciate just how close the site is to Hornsby Town Centre in the May 2024 drone video, as we take flight from the Hornsby Aquatic and Leisure Centre and head over the site.


February 2024 – April 2024

The focus during February to April 2024 has remained on the construction of the retaining wall structures around the quarry void. In particular, the walls on the eastern and north-western edge of the Quarry Void.

A significant milestone was achieved in February with the placement of the final precast panel wall section for the project.

A 350 Tonne crane was used to lift the panels into place. The crane needed a maximum lift radius of 48m, and seven semi-trailer loads of counterweights. The largest precast panel was 4.65m tall and over 9 Tonnes in weight.

Progress is also being made on the concrete pavement access roads.


December 2023 – January 2024

As 2023 ends and 2024 begins, anticipation is growing as the various improvements across the site start coming together to reveal the final stabilised landform. Continued progress across all key milestones has the project on track for completion this year. The worksite was closed for the Christmas/New Year break from 22 December to 8 January 2024.

During December and January resources have been focused on three key areas.

  1. The final section of the drainage works with the completion of the open channel section.
  2. The first section of concrete pavement along the Northern Access Track (NAT).
  3. The retaining wall adjacent to the access road on the eastern edge of the Quarry Void. Due to its length, approximately 120m and height, over five metres in parts, the wall it is being constructed in eight sections.

2025

July 2025

The Southern Lookout take shape

We are excited to share a behind-the-scenes look at the construction and transportation of the Southern Lookout viewing deck and access stairs, located at the historic Crusher Plant site at Hornsby Park.

Our contractors are installing these landmark features, which will transform the way residents and visitors experience the bushland setting on the site of the old Hornsby Quarry.

These prefabricated steel structures have been expertly designed for durability, safety, and accessibility, and represent a major milestone in the delivery of Hornsby Park.

The Southern Lookout will offer panoramic views across the former Hornsby Quarry and surrounding bushland, creating a unique space that connects people with the natural landscape and honours the area’s heritage.


November 2024 – February 2025

We are excited to announce that all key elements in the Bulk Earthworks stage of the Hornsby Quarry Rehabilitation were completed, by the end of February 2025. This project has involved large scale earthworks and stabilisation works that have now created a stable foundation for the future embellishment works on the former quarry site.

From November 2024 to the end of February 2025, the earthworks across the site were finalised, including in the quarry void, the zig-zag pathway and Old Mans Valley.  These areas were hydromulched to protect these open areas from wind and erosion.

The last activity undertaken by Ditchfield Contracting on site was to demobilise their plant and equipment including excavators, trucks and site sheds from the site. Check out the photo of their sheds leaving the site.

The site was then handed back to Council and this allowed us to undertake insitu stabilisation and sealing of several roads / shared zones around the site. Check out the impressive process of stabilising the road material and application of the seal to the roads in the “Hornsby Quarry Pavement Stabilisation and Sealing” Video. These works will ensure the pavements are protected from potential erosion, as the project moves into a transitional phase, awaiting future embellishment projects across the site.

The Vision

A dramatic transformation is taking place at the old Hornsby Quarry.

In the raised floor of the quarry void, a water body is expected to be created, fed by groundwater and rainfall. From the water’s edge, the landform will rise up, broadly forming an amphitheatre, with graded entry from the western and northern sides. Within the eastern face of the quarried walls, the geological formation of a volcanic diatreme will be preserved. Extensive rehabilitation of the surrounding bushland will be undertaken to create a bushland backdrop for the amphitheatre.

Once the earthworks are completed, subject to future design and approvals, varied settings including landscape regeneration, community, cultural and recreation opportunities will be provided in Old Mans Valley, around the old Crusher Plant and in the former fill profile area in south-west corner of the site.

By completion, the old quarry will form a dramatic centrepiece to the new park.

Go to Top